Boiler World Update

Written by 3:54 pm All

Steam Boiler Commissioning: Integrating Cleaning, Passivation and Corrosion Protection from Day One

Conventional boiler commissioning treats cleaning and passivation as successive operations. This article presents an alternative approach using film-forming amines to perform both functions during the same boil-out cycles. A field application on a 5 t/h fire-tube boiler illustrates how this method can simplify commissioning while initiating corrosion protection from day one.

Introduction

Every new steam boiler undergoes extensive inspections before entering service. Pressure tests are completed, instrumentation is calibrated, and the installation is verified against design specifications. From a mechanical perspective, the boiler may be considered ready. Chemically, however, the situation is different.

Fresh steel surfaces remain highly reactive after fabrication, transport, storage, and hydrostatic testing. Oils, mill scale, welding residues, and loose iron oxides may still be present within the boiler and the associated water-steam cycle. Even after cleaning, newly exposed metallic surfaces can remain vulnerable to corrosion during filling, heating, and the first steam-generation cycles.

Successful commissioning should therefore go beyond contaminant removal. It should establish a controlled transition from cleaning to surface conditioning and early corrosion protection. This is the purpose of an integrated commissioning strategy: preparing the boiler for operation while protecting its metallic surfaces from day one.

Why Passivation Matters

For decades, alkaline boil-out procedures have been widely used to prepare new and refurbished steam boilers before startup. Their primary objective is to remove oils, grease, welding residues, loose iron oxides, and other construction contaminants that could compromise water quality, heat transfer, and subsequent treatment performance.

When properly designed and executed, these cleaning procedures remain an essential part of boiler commissioning. However, cleaning alone does not ensure that the newly exposed metallic surfaces are protected. Fresh carbon steel remains chemically reactive and may be susceptible to oxygen-related corrosion during filling, heating, intermediate rinsing, and the first steam-generation cycles.

Once contaminants and loosely adherent oxides have been removed, the newly exposed steel surface must be converted from a reactive state into a protected state. This is the purpose of passivation. In a conventional process, controlled chemical and thermal conditions promote the formation of a stable, adherent protective iron oxide layer on the steel surface. This layer acts as a barrier between the metal and the surrounding water, reducing the electrochemical reactions responsible for corrosion. Without this protective layer, or an alternative surface-protection mechanism, the benefits of cleaning may be compromised by rapid oxidation of the freshly exposed steel.

Conventional boil-out procedures may also require highly alkaline chemicals, wastewater neutralization, multiple rinsing stages, and close operational control. If protection is treated as a separate step, a period of vulnerability may remain between the completion of cleaning and the establishment of stable operating chemistry.

Cleaning removes contaminants. Passivation creates the protective surface conditions required for reliable long-term operation.

From Sequential Operations to an Integrated Process

In conventional boiler commissioning, cleaning and passivation are generally performed as two successive operations. The boiler is first cleaned to remove oils, grease, loose oxides, and construction residues. It is then rinsed, refilled, and subjected to a separate passivation stage to stabilize the newly cleaned metallic surfaces before normal operation begins.

The film-forming amine approach changes this sequence by combining cleaning and surface passivation within the same commissioning process. While contaminants are removed during the boil-out, the film-forming amines adsorb onto the exposed metallic surfaces and begin establishing a protective hydrophobic film.

By carrying out cleaning and passivation simultaneously, this integrated approach can reduce the number of separate treatment stages, optimize water use and wastewater generation, shorten commissioning time, and limit the period during which freshly cleaned steel remains unprotected.

The objective is not to eliminate the essential cleaning function, but to perform it more efficiently while initiating corrosion protection from the earliest stages of commissioning.

Film-Forming Amines: A Modern Commissioning Strategy

Film-forming amines provide a surface-oriented approach to boiler commissioning. When incorporated into the cleaning solution, they allow contaminant removal and metallic surface conditioning to take place during the same operating sequence.

Unlike conventional passivation, which relies primarily on the controlled formation of a protective iron oxide layer after cleaning, film-forming amines adsorb onto wetted metallic surfaces. Their molecular structure promotes the formation of a thin, hydrophobic film that reduces direct contact between water and the metal.

In this article, “amino-passivation” refers specifically to the simultaneous cleaning and film-forming amine conditioning of metallic surfaces during the boil-out procedure.

As contaminants are progressively removed during the boil-out, newly exposed metallic surfaces can begin to be protected without waiting for a separate passivation stage. This limits the period during which fresh carbon steel remains directly exposed to water and oxygen.

Depending on their formulation and operating conditions, film-forming amines can also be transported through the steam phase and contribute to the protection of the feedwater, steam, and condensate circuits. The commissioning strategy can therefore extend beyond the boiler itself and support the progressive stabilization of the complete water-steam cycle.

This approach does not remove the need for appropriate preliminary mechanical cleaning or flushing when significant construction debris, heavy deposits, or strongly adherent oxides are present. The initial condition of the system must always determine the cleaning protocol.

A Simplified Amino-Passivation Procedure

One of the main operational advantages of amino-passivation is its simplicity. Cleaning and passivation are performed during the same boil-out cycles, without adding a separate passivation stage after cleaning.

The procedure follows a straightforward sequence:

  1. Fill the boiler with water and the film-forming amine cleaning formulation.
  2. Heat the boiler and carry out the first boil-out.
  3. Drain the boiler to remove the contaminants released during cleaning.
  4. Refill the boiler and repeat the boil-out.
  5. Drain and rinse before the final filling and transition to normal operation.

During both boil-out cycles, contaminants are progressively removed while the film-forming amines adsorb onto the newly exposed metallic surfaces. Cleaning and protection therefore develop together throughout the procedure.

Compared with a conventional sequential process, this method removes the need for a separate passivation operation. It reduces the number of commissioning stages, limits handling requirements, and simplifies field execution. The use of a biodegradable formulation can also facilitate effluent management by avoiding the neutralization requirements associated with strongly alkaline conventional treatments, subject to applicable site discharge requirements.

The result is a shorter and more practical commissioning process: fill, boil, drain, and repeat, while cleaning and protecting the boiler from the first cycle.

Case Study — Amino-Passivation of a 5 t/h Fire-Tube Boiler

The amino-passivation procedure was implemented during the commissioning of a new industrial fire-tube steam boiler.

ICI Caldaie 440F25 fire-tube boiler commissioned using the two-cycle amino-passivation procedure.
Figure 1 — ICI Caldaie 440F25 fire-tube boiler commissioned using the two-cycle amino-passivation procedure.

System specifications

Manufacturer and modelICI Caldaie 440F25
Boiler typeFire-tube steam boiler
Steam capacity5 t/h (11,000 lb/h)
Operating pressure25 bar (360 psi)

Project objective

The objective was to clean the internal metallic surfaces and establish early corrosion protection before routine steam production, while simplifying the conventional commissioning sequence.

Commissioning sequence

  1. Preliminary rinse
  2. First filling with the amino-passivation formulation
  3. First boil-out
  4. Drain and rinse
  5. Second filling with the amino-passivation formulation
  6. Second boil-out
  7. Drain and rinse
  8. Final filling
  9. Steam blow and transition to routine operation

This two-cycle procedure enabled cleaning and surface protection to take place simultaneously, without requiring an additional passivation stage after the boil-out operations.

Operational results

The two-cycle procedure was completed without a separate conventional passivation stage. During the successive boil-outs and draining operations, the boiler water became progressively clearer as construction residues and loose contaminants were removed.

The commissioning team observed:

  • progressive improvement in boiler-water appearance;
  • effective removal of loose construction contaminants;
  • simultaneous cleaning and conditioning of the internal metallic surfaces;
  • simplified execution compared with separate cleaning and passivation operations;
  • reduced handling and fewer commissioning stages;
  • a direct transition from the final rinse to filling and routine boiler-water treatment.

The boiler was commissioned according to the planned sequence, with no additional passivation operation required after cleaning.

Photographic evidence

The visual evolution of the boiler water was documented throughout the procedure. The photographs below compare the water appearance after the preliminary rinse, the first boil-out, and the second boil-out, providing a direct field indication of the progressive removal of construction residues and loose contaminants.

Visual appearance of the boiler water after the preliminary rinse.
Figure 2 — Visual appearance of the boiler water after the preliminary rinse.
Visual appearance of the boiler water after the first amino-passivation boil-out.
Figure 3 — Visual appearance of the boiler water after the first amino-passivation boil-out.
Visual appearance of the boiler water after the second amino-passivation boil-out.
Figure 4 — Visual appearance of the boiler water after the second amino-passivation boil-out.

Lessons learned

This field application confirmed that cleaning and passivation can be successfully combined within the same boil-out procedure. The two-cycle sequence was straightforward to implement and did not require a separate passivation stage after cleaning.

The main operational benefit was not the elimination of cleaning, but the integration of surface protection into the cleaning cycles themselves. This reduced the number of commissioning operations while limiting the period during which freshly cleaned steel remained unprotected.

The progressive improvement in water appearance between the two cycles provided a clear visual indication of contaminant removal. The procedure could therefore be followed easily by the commissioning team, without adding unnecessary complexity to the startup schedule.

Amino-passivation should ultimately be viewed as a practical optimization of boiler commissioning: fewer separate operations, simplified execution, and corrosion protection initiated from the first boil-out.

Conclusion

Cleaning and passivation are both essential steps in preparing a new steam boiler for reliable operation. In conventional commissioning, they are generally performed as successive operations. The film-forming amine approach makes it possible to combine them within the same boil-out cycles.

By allowing contaminants to be removed while newly exposed metallic surfaces are progressively protected, amino-passivation simplifies the commissioning sequence and limits the corrosion-vulnerability period between cleaning and routine operation.

The field application presented in this article demonstrates the practical value of this integrated approach. Two successive cycles, fill, boil, drain, and repeat, were used to clean and condition a 5 t/h fire-tube boiler without requiring a separate passivation stage.

This approach does not change the fundamental objective of boiler commissioning. It improves how that objective is achieved: fewer separate operations, simpler field execution, more efficient use of water and chemicals, and corrosion protection initiated from day one.

The goal is not simply to place a boiler into service. It is to start it clean, protected, and ready for reliable long-term operation.

Author:

Logan Manaranche
Vice President
ODYSSEE USA INC.

References

[1] J.P. Labbé, J. Lédion, F. Hui, Infrared spectrometry for solid phase analysis: Corrosion rusts, Corrosion Science 50 (2008) 1228-1234 

[2] P. Leroy, Calcium et corrosion, thèse, Université ParisV, 1991

[3] L. Legrand, P. Leroy, Prévention de la corrosion et de l’entartrage dans les réseaux de distribution d’eau, CIFEC, Paris, 1995.

[4] Y. Cudennec, A. Lecerf, Étude des mécanismes de formation des oxy-hydroxydes de fer ; hypothèses de transformations topotactiques.

[5] CHEMetrics. Filming amine (aliphatic amine) visual test kits [Internet]. [cited 2025 Aug 11]. Available from: https://www.chemetrics.com/product/filming-amine-aliphatic-amine-visual-test-kits/?srsltid=AfmBOorAnmOF_Q6iBWx-vHT622yqA33dthT-2DVLPzGu4kg0Tp4ChK_p

[6] Hach. Film-forming amine kit [Internet]. [cited 2025 Aug 11]. Available from: https://ca.hach.com/film-forming-amine-kit/product?id=64354117731

[7] Taylor Technologies. Colorimeter reagent pack – filming amine (Rose Bengal, 0.8–0 ppm) [Internet]. [cited 2025 Aug 11]. Available from: https://taylortechnologies.com/products/colorimeter-reagent-pack-filming-amine-rose-bengal-0-8-0-ppm 

[8] International Association for the Properties of Water and Steam (IAPWS). Technical Guidance Document: Application of Film Forming Substances in Industrial Steam Generators, IAPWS TGD11-19, 2019. Official IAPWS document

[9] International Association for the Properties of Water and Steam (IAPWS). Application of Film Forming Substances in Fossil, Combined Cycle, and Biomass Power Plants, IAPWS TGD8-16(2019). Official IAPWS presentation

[10] ODYSSEE Environnement. Field commissioning records and photographic documentation for the ICI Caldaie 440F25 boiler amino-passivation procedure.

FAQs

What is integrated steam boiler commissioning using film-forming amines?
Integrated steam boiler commissioning is an approach that combines cleaning and corrosion protection within the same boil-out cycles. Instead of performing conventional alkaline cleaning followed by a separate passivation stage, film-forming amines are added during the boil-out to remove construction contaminants while simultaneously conditioning exposed metal surfaces. This helps reduce commissioning steps and initiates corrosion protection from the first cleaning cycle.
How does film-forming amine passivation protect a new steam boiler?
Film-forming amines adsorb onto wetted metallic surfaces and form a thin, hydrophobic protective film. This film reduces direct contact between water and freshly exposed steel, helping limit corrosion reactions during filling, heating, and initial steam-generation cycles. Depending on the formulation and operating conditions, the amines may also support protection throughout the feedwater, steam, and condensate circuits.
What are the advantages of simultaneous cleaning and passivation during boiler commissioning?
Simultaneous cleaning and passivation can simplify boiler commissioning by combining contaminant removal and surface conditioning into the same boil-out procedure. Potential benefits include fewer commissioning stages, reduced chemical and water handling, lower wastewater generation, shorter commissioning time, and reduced exposure of freshly cleaned steel to corrosion. The approach can be particularly useful for new and refurbished fire-tube steam boilers.
How is a film-forming amine boil-out performed on a new steam boiler?
A typical film-forming amine boil-out involves filling the boiler with water and the appropriate treatment formulation, heating and completing the first boil-out, draining and rinsing, then repeating the filling and boil-out cycle. After the final drain and rinse, the boiler is filled and transitioned to normal water treatment and operation. The exact chemical formulation, concentration, temperature, duration, and number of cycles should be determined according to the treatment program and boiler manufacturer’s requirements.
Can amino-passivation eliminate the need for a separate conventional boiler passivation stage?
In an appropriately designed commissioning program, film-forming amine amino-passivation can combine cleaning and surface conditioning during the same boil-out cycles, potentially eliminating a separate conventional passivation operation. A field application on a 5 t/h fire-tube boiler demonstrated a two-cycle process that cleaned and conditioned the internal metallic surfaces without an additional passivation stage. However, the suitability of the approach depends on the boiler’s initial condition, contamination level, treatment formulation, and applicable commissioning requirements.